WMF Projects/OWA/2011q2 plan
Appearance
< WMF Projects | OWA
- March 7 -> OWA DB schema formulated
- March 14 -> (owa DB work) -> CentralNotice Bastardization plan formulated (we intend to use the CentralNotice code as a starting point, with a goal of fully modular code, but don't plan to fully modularize it yet)
- March 21 -> OWA DB changes complete
- March 28 -> (owa API work)
- April 4 -> OWA custom API events complete -> MW Data Delivery Mechanism complete (CentralNotice style or whatnot)
- April 11 -> (owa report work)
- April 18 -> (owa report work)
- April 25 -> MW Extension Complete
- May 2 -> OWA initial reports complete
- May 9 -> (iterate on reports)
- May 16 -> (iterate on reports)
- May 23-> Special JS OWA requirements complete -> adding special JS into MW
- May 30 -> Integration testing
- June 6 -> (integration work)
- June 13 -> Staging/Deployment
- June 20 -> (take care of issues)
- June 27 -> (take care of issues)