Notable action items

[edit]
  • Multimedia is blocked by ops, QA, and OOJS review for their impending release
  • Zero blocked by ops on review for portal
  • Growth still awaiting code review from platform/core RE deletion logging enhancement
  • Chris McMahon is OOO 31 Mar and 1 Apr, contact Zeljko, Antoine or Greg G if you need QA assistance

Language

[edit]
  • LU rewrite has been deployed. Extensions just migrated to json will take a bit longer to update (migration has to go through the train first).
  • #80 Writing middle layer for ElasticSearch - bootstrap and tm works now with some quirks (Thanks Nik)
  • Just FYI: Summer time starts in most of Europe next week

QA

[edit]

Clearing off the backlog with

  • VE
  • infrastructure
  • hiring
  • Wikimania
  • 3rd party accounts

in order to devote significant time to the next MobileFrontend iteration

Note: Chris is OOO 31 Mar and 1 Apr, contact Zeljko, Antoine or Greg if you need QA assistance

Multimedia

[edit]

Growth

[edit]

Continued work on non-linear tours and GettingStarted and GuidedTour cleanup. Sam started a patch (https://gerrit.wikimedia.org/r/#/c/120806/) to provide a cookie module on the client that works the same as the server (mediawiki.cookie). It's a WIP currently.


Parsoid

[edit]
  • Parsoid/Deployments
  • good progress on HTML templating, PHP port hopefully this week
  • lots of improvements in image handling, some DOM spec updates in that area

Ops

[edit]
  • JVM App Deployment:
   ** coming along!  http://archiva.wikimedia.org
   ** working on deployment, will start writing lots of docs soon.
  • varnishkafka
 ** Mark and Otto to do some transatlantic troubleshooting soon.

Mobile

[edit]
  • #70 - one thing still missing (VE theme split)
  • #87 - would be good to have sooner than later so that we can test VE easily, scheduled

Zero

[edit]

Analytics

[edit]
  • #88 - Event logging issue caused this, talking with Ori to transition EventLogging to analytics team. But graphs are updating though there is lost data for the two days EL was down.

Flow

[edit]
  • sharing code!: client storage code with Mobile, also Mobile's approach to loading templates (hogan/handlebars, basically the same)
  • #84 Parsoid CSS in progress

VisualEditor

[edit]
  • Collaborating with mobile and Parsoid as usual
  • Worked with lang eng to get LocalisationUpdate changes merged and deployed, working now modulo pending bug fixes
  • Working on oojs-ui-ifying UploadWizard
    • Goal: embeddability in VE
    • MarkH says they don't have time for it until May; that's OK, RobM will just do it and ask MarkH for review