High Level Timeline
[edit]Done | Now | Next | Future |
---|---|---|---|
AQS 2.0 on production | SDS 2.5.1 | SDS 2.5.2 | SDS 3.4.1 |
Commons Impact Metrics Prototype | AQS 2.0 Launch | Data Dumps 2.0 | |
Commons Impact Metrics Implementation |
Current Initiatives & Projects
[edit]OKR / Committed / Essential | Initiative (Project Pages) | Epics (Phab Tickets) | Status |
---|---|---|---|
SDS 2.5.1 | Metrics Platform | Add core interaction API to PHP client library | Done |
Add core interaction API to Java client library | Done | ||
Add core interaction API to Javascript client library | In Process | ||
Migrate first adopting team to core interactions API client libraries | Up Next | ||
Onboard second adopting team | Up next | ||
Onboard third adopting team | Backlog | ||
Onboard fourth adopting team | Backlog | ||
SDS 2.5.2 | Metrics Platform | Architect solution for Control Plane | Up Next |
Create UI Prototype for Control Plane | Up Next | ||
Essential Work | AQS 2.0 | Device Analytics Implementation | Shipped |
Geo Analytics Implementation | Shipped | ||
Media Analytics Implementation | Shipped | ||
Page Analytics Implementation | Shipped | ||
Edit Analytics Implementation | Shipped | ||
Editor Analytics Implementation | Shipped | ||
Sunset AQS 1 | In process | ||
AQS 2.0 Launch | Up Next | ||
Committed Work | Commons Impact Metrics | Community Consultation Phase 1 | In Process |
Technical Discovery Report | Done | ||
GLAM Prototype Data Model and Implementation Plan | Done | ||
Design Research Report | In Process | ||
Prepare first prototype | In Process | ||
Prepare prototype for user testing | In Process | ||
Prepare presentation & workshop for GLAM Wiki Conference | Up Next | ||
Conduct Presentation & Workshop @ GLAM Wiki conference | Up Next | ||
Gather learnings and plan next phase of work | Up Next | ||
Community Consultation Phase 2 | Up Next | ||
Essential Work | Data Dumps 2.0 | Vertical slice / proof of hypothesis | Paused |
MVP that can replace Dumps 1.0 for right to fork | Backlog | ||
Stop making Dumps 1.0 | Backlog | ||
Essential Work | "other" Dumps | Plan strategic approach to "other" data dumps | Backlog |
Discovery phase for "other" dumps | Backlog | ||
SDS 3.4.1 | Serving Data | Plan strategic approach to serving data publicly | On hold |
Backlog are epics/milestones planned for future quarters
Up Next are epics/milestones for current quarter
In Process are epics/milestones actively in development
Done are epics/milestones that are implementation complete
Shipped are epics/milestones that are on production and/or publicly released